Case Study · Office · Wynwood, Miami

A wall of moving water

From a bare concrete shell to a full-length water wall, step by step.

A wall of moving water
System
Glass water wall with recirculating basin
Setting
Office reception, Wynwood, Miami
Scope
Structure, waterproofing, basin, glass, lighting
Timeline
June 2022 – February 2023

Water as the first impression

The brief was a single, continuous surface of moving water running the length of the reception wall, the first thing anyone sees stepping off the elevator.

A water wall this size is mostly invisible engineering: structure, waterproofing, a recirculating basin and lighting, all hidden behind glass. This is how it came together.

01 · The shell

June 2022

We started in a bare concrete shell with fresh steel framing, walking the space with the builders to plan where the wall would go and how water, power and drainage would reach it.

A wall of moving water — June 2022A wall of moving water — June 2022A wall of moving water — June 2022

02 · Laying it out

August 2022

Every line was set with a laser before anything went up: a wall of falling water shows the slightest error, so the layout has to be exact.

A wall of moving water — August 2022

03 · The backing

August 2022

Solid timber backing was fixed across the wall to carry the weight of the panels and glass, with every member checked for level and plumb.

A wall of moving water — August 2022A wall of moving water — August 2022A wall of moving water — August 2022

04 · Basin and frame

October 2022

The black basin that collects and recirculates the water was set along the base of the wall, with the frame built up around it.

A wall of moving water — October 2022A wall of moving water — October 2022A wall of moving water — October 2022

05 · Waterproofing everything

Oct – Nov 2022

Behind the glass, the whole wall was sealed and waterproofed. It is the least glamorous step and the one that matters most.

A wall of moving water — Oct – Nov 2022A wall of moving water — Oct – Nov 2022A wall of moving water — Oct – Nov 2022A wall of moving water — Oct – Nov 2022A wall of moving water — Oct – Nov 2022A wall of moving water — Oct – Nov 2022

06 · The glass

November 2022

The textured glass panels went in, set into the frame so the joints read as quiet lines across the wall.

A wall of moving water — November 2022A wall of moving water — November 2022A wall of moving water — November 2022A wall of moving water — November 2022

07 · First light

November 2022

With the lighting on, the wall started to glow. Then the water was switched on and tuned until it ran evenly across every panel.

A wall of moving water — November 2022A wall of moving water — November 2022

08 · Finished

Jan – Feb 2023

The finished wall runs the length of the reception, a constantly moving surface of light and water behind the front desk.

A wall of moving water — Jan – Feb 2023A wall of moving water — Jan – Feb 2023A wall of moving water — Jan – Feb 2023A wall of moving water — Jan – Feb 2023A wall of moving water — Jan – Feb 2023A wall of moving water — Jan – Feb 2023